History: first monolithic slab poured, foundation reinforcement under way
In early October, excavation at the History site was almost complete, and on the night of 13 October the first monolithic slab was poured. By 27 October the crew was…

Life Style at 53 Angisa Street is built: the monolithic frame, the Alucobond ventilated façade, the windows and two Mitsubishi lifts are in place. Interior finishing of the common areas is under way. Handover is scheduled for Q4 2026.
In early October, excavation at the History site was almost complete, and on the night of 13 October the first monolithic slab was poured. By 27 October the crew was…
On 30 September, the day after the PRESALE opened, AB Development presented IMPERIAL · BATUMI to Batumi real estate agents. Partners heard about the concept of the club…
On 29 September AB Development opened the PRESALE of the IMPERIAL club residence in Batumi’s historic centre. It is a 16-storey building with a 7-metre grand lobby, a…